on 08-18-2008 11:30 AM
Where we maintain the currency conversion in PS
Hi Friends,
Hope all are doing well.I have one doubt .Where we maintain the currency conversion in Project system ?
Suppose we are doing the costing according to american dollar but at the end when we are going to check the report in information system we want the values in indian currency.
So in PS where we are maintaining the formula and currency value so that we can get the report in Indian currency.
Is there any way so that I can get the exact value according to today's date.
Please reply as it is urgent.
Regards
Edited by: Amit Kumar on Aug 18, 2008 12:43 PM
hi amit,
you need to maintain exchange rates , from dollar to ind, ind to dollar , u can find in SPRO ,SAPNETWEAVER,GENERAL SETTINGS,CURRENCIES...plz read the same and do the setting i have done this long before when i was not completely aware..
regrds
pushpa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
ansd.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Amit,
Please use T.code OB07 to define the Exchange Rate usage and OB08 to define the exchange rates. You may read the attached document for more clarity.
Hope this helps.
Thanks
Venu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.