currency conversion

Former Member
0 Kudos

Where we maintain the currency conversion in PS

Hi Friends,

Hope all are doing well.I have one doubt .Where we maintain the currency conversion in Project system ?

Suppose we are doing the costing according to american dollar but at the end when we are going to check the report in information system we want the values in indian currency.

So in PS where we are maintaining the formula and currency value so that we can get the report in Indian currency.

Is there any way so that I can get the exact value according to today's date.

Please reply as it is urgent.

Regards

Edited by: Amit Kumar on Aug 18, 2008 12:43 PM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi amit,

you need to maintain exchange rates , from dollar to ind, ind to dollar , u can find in SPRO ,SAPNETWEAVER,GENERAL SETTINGS,CURRENCIES...plz read the same and do the setting i have done this long before when i was not completely aware..

regrds

pushpa

Answers (2)

Answers (2)

Former Member
0 Kudos

ansd.

Former Member
0 Kudos

Hi Amit,

Please use T.code OB07 to define the Exchange Rate usage and OB08 to define the exchange rates. You may read the attached document for more clarity.