on 08-18-2008 11:10 AM
Dear all,
let us imagine,i have created return order for customer return.After completing the post goods receipt,Quality team will check & repair the product.
Mow i would like to send the product again to customer.How can i do in SAP?
idea pls.........
done
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
To return the Material, Delivery Free Of Cost process cycle will have to be executed.
Sales Order (Delivery Free of Cost Type) >> Delivery >> Billing
Regards,
Rajesh Banka
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Veera
Once the quality is passed the rejected material, you can again follow the normal OR-LF-F2 process. That is create sale order, delivery & billing.
However, if you want to track that the material sold is a returned one, you can create a sale order referencing the origin invoice so that in document flow, you can see all preceding documents.
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
The same can be tried with T code MB1B with movement types 311 or 309E or 311E
This will move that stock from unrestricted to sales order stock which i think that you can bill again to the customer
Pls try this and get back to me if helpful
Raja
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.