on 08-18-2008 7:29 AM
Dear friends,
Can anybody explain how the "Transportation planning status" (VBUK-TRSTA) is updated in the delivery document.
As per our configuration transportation planning status is A (Not processed). But for few deliveries it is blank (Not relevant) and therefore we can't create shipment documents.
Please provide a solution for above.
Thanks,
Jeewana
Hi there,
When defining the routes, there is a field called "Rel.Transport". If you check the field, the particular field will be relevant for transport planning & you can create shipments for that route. Go to T-code 0VTC, check the notes by clicking F1 on the "Rel.Transport" field.
The VBUK-TRSTA is updated accordingly. If there is no check in the field, the table will be updated as not relevant. If shipment doc is created, it will update the status of it accordingly.
Hope this clarifies your question.
Regards,
Sivanand
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hii.,
Thank you very much for your feedback.
Points granted.
Jeewana.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.