Hi PS experts,
How do we know that the AUC's are created and how do we know status of all the cost is posted to AUC(before settlement rule)? How can we find out the status?
Can anyone tell me how to see it?
Thanks,
Sanju.
Go to CJ20N - Edit - WBS element - Investment Programs - Asset Under Construction..It should show AUC when you click Asset under construction. System Status of the WBS should say AUC.
I guess when you are saying status of cost you mean how much cost is posted/settled on AUC. Go to that AUC(AS02) and click on the tab on the upper left side(Asset Explorer), it shows the amount posted on it.
Hope it helps.