on 08-15-2008 8:49 PM
Dear All,
On the Work order, Check material availability functionality, if I change the Offset lead-time how can I configure to automatically change the Requirement date for Reservation.
Thanks!
Hi,
Go to COHV and do the avaibility check again.
Regards,
.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
if you change the offset entry automatically the requirement time will change ,kindly check with some higher or negative value
regards
thyagarajan