on 08-15-2008 8:07 PM
All,
All figures shown on the cost overview report which is triggered from the project structure should be in company code currency NOT USD. Is there any config setting which will show results in company code currency but not at controlling area level.
Request your input in this regard.
Regards
Kasi
cloned CN41 and replaced Object currency values from RPSCO table
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kasi,
Please try setting the project currency in the project profile OPSA under 'Organization' tab to meet your currency requirement. Otherwise you can also use settings in OPSB for setting the planning currency as required.
hope this helps.
Thanks
venu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.