on 08-14-2008 1:36 PM
Hi,
Anybody knows how can I turn default this field "Follow-On Document" with the value "PO or Contract".
Every time when I try to create a Bid Invitation, this field show me up "PO" such default.
See the print of the screen: [SCREEN|http://geocities.yahoo.com.br/pedrosapmm/doc.jpg]
Tks,
Pedro
Hi Pedro,
This works the other way. Please make sure that both the indicators are not selected. Then you will "Purchase Order and Contract" as default.
SPRO -> Supplier Relationship Management -> SRM Server -> Cross-Application Basic Settings -> Define Transaction Types -> BUS2200
and for all your BID transaction types (PO and Contract must be not be selected).
Hope this solves your problem.
Regards
Kathirvel
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In SPRO in define transaction types select the object BUS2200 and click on transaction types. Then select your transaction type, normally 'BID' and select details button. Under process control in detail screen, select both purchase order and contract. Then both will appear when you create a bid invitation.
Rgds,
RRK