How order start date and order finish date getting calculated in APO sysytem.
with regards
Ram
Its based on variaty of factors such as production leadtime defined in PPM, production calenders etc. the timing of order start date/time could be governed by availability of resource, components, different calenders etc.
The way you see it in different views like product views and planning book views could depend on the time zones too.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
With factors defined in Strategy profile like planning direction...backward,forward,forward + reverse or backward + reverse or finite scheduling or infinite scheduling..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.