on 08-14-2008 11:38 AM
Hi,
We are in the process of upgrading from SAP 4.7 to ECC 6 in the
production server. At the outsetthe following broad phases to be
carried out.
1. Prepare
2. SAPUP I
3. SAPUP II
Can we keep some intervals between these phases and can the developementserver be released for users. Especially between SAPUP I & SAPUP II can
we have some time interval to plan our downtime (Specific to SAPUP II) ?
Please suggest .
Regards
Karthikeyan S
I´m not sure what you mean with phases "SAPUP I" and "SAPUP II".
Check the upgrade guide, it has a detail graphics what you can do at which place, when users can work with the system and when not.
Markus