Dear all

I want to run MRP as per MRP area (storage loc) wise

plz guide me

Former Member
replied

Hi,

In scope of planning In OM0E

You need to enter the plants in sequence so that system will plan all the plants materials in sequence.

Inn SPROProduction>Material Requirements Planning-->Define Parallel Processing in MRP

Here you maintain the server and sessions so that system will decide to run the MRP in different sessions so that MEP will come with results very fast

You have to mention the server name of Production Server.

For this from system menu you can get the server name.

Go to System---->Status and on the System:Status screen, you can find the server name in the Host data .

Or you can also consult your BASIS person.