Dear all

I want to run MRP as per MRP area (storage loc) wise

plz guide me

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi,

Refer below link..

http://www.sap123.com/showthread.php?t=57

Regards,

R,Brahmankar

Former Member
0 Kudos

Dear all

I have created scope of planning.

When i entered this scope of planning in MD01 ystem is trouching a error

1)"Planning run for scope of planning is only possible in parallel mode"

when i tick on parallel processing on md01. this error is came

2)Please check the destinations for parallel MRP

Message no. MD251

Diagnosis

No destinations have been entered in Customizing or none of the the destinations (application server) entered are active.

In Customizing for MRP, you define the logical destinations (servers) to be used for parallel processing.

guide me

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi,

In scope of planning In OM0E

You need to enter the plants in sequence so that system will plan all the plants materials in sequence.

Inn SPROProduction>Material Requirements Planning-->Define Parallel Processing in MRP

Here you maintain the server and sessions so that system will decide to run the MRP in different sessions so that MEP will come with results very fast

You have to mention the server name of Production Server.

For this from system menu you can get the server name.

Go to System---->Status and on the System:Status screen, you can find the server name in the Host data .

Or you can also consult your BASIS person.

Regards,

R.Brahmankar

0 Kudos

This message was moderated.

Former Member
0 Kudos

Hello Carlos,

This discussion is already closed. Please open a new thread with your queries.

Regards,

Rohit

0 Kudos

Ok, Thanks you!

Answers (1)

Answers (1)

former_member196398
Active Contributor
0 Kudos

Surendra,

Use transaction "OM0E" to define scope of planning for individual MRP areas and based on this scope of planning you can create variants which can be scheduled using MDBT to run in back ground.

Regards,