on 08-14-2008 9:10 AM
Hi Gurus
I have created a Bid invitaion which has a No approval workflow , I have checked in SWIA it has been marked for "release" and there is no error log in SWPR. The problem is the Status of Bid invitation it is on Awaiting approval ...........and when trying to change the document it gives me a message Document is still being processed in the background; Try again later
where can I check to see where is it hanging ?
Dear,
First check to SM12 with the user id that create the bid invitaiton, also check if there's any bidder lockin the bid.
If all the purchaser and the bidder is not currentcly change the document, then use SM12 to unlock the entires,
or in some case it just WF hang ,
You can try to push the hanging workflow using FM : BBP_PD_BID_STATUS_CHANGE_WF , enter the Header GUID and status =1 ,then execute and check again.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.