Dear All,
i am facing an issue while making BOM transfer into project (T-code CN33). After executing transaction, cn33, materials are not getting assigned into network activties automatically, rather going for manual assignment. I have mainatined reference point for both activity & BOM. I am using WBS BOM for transfer of components into project. Please advise me to make automatic assignment of materials into project after BOM transfer & to avoid manual allocation.
Thanks,
T Code CN38, ensure you've maintained both (BOM and Network) the field names as RFPNT
Regards