Item availability in background for make to order scenario

Former Member
0 Kudos

hi to all

i have a requierment for our project ,out client process is make-to order . once Sales creates the sales order this order will go for process order converted into production order.onec the goods produced against this sales order by doing MIGO the stock is posted to the unrestricted storage loaction.This is about the process.

My requirement is as an when the material is posted to storage location i have to do item availability manualy in the sales order.This will be done with checking with stock over view MMBE. But the client requirement is that process of confirming the item availability in the back ground .That is as an when the stock is produced against this sales order the item availability (schedule line ) should be confirmed in the back ground.

I need your valuable sloution to this scenario. My requirement is very critical as this requirement has come after golive. I have to do this at the earliest.

Looking for the reply

Regards

madhu

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi All

Since no response for this requirement, I am closing this issue

Regards

Madhu