on 08-13-2008 2:41 PM
Dear guru
is it possible to create a shipment via VT01N where the status planned is already setted
Hi,
Do you mean a blank shipment without any deliveries in it? With VT04 and by creating variants for the collective processing, you can have shipments automatically created and have planning button pressed in.
Regards,
MdZ
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Andrea,
Through variant maintenance you can get your requirement.
To maintain the variant please go through this SAP help link
http://help.sap.com/saphelp_47x200/helpdata/en/93/743cba546011d1a7020000e829fd11/frameset.htm
I hope it will help you,
Regards,
Murali.