on 08-13-2008 6:33 AM
Hi
I wanted to know from where the material staging time in the sales order is picked. In my case, Iam doing a MTO wherein the material is not available, but when the order is raised, lets say at 12:00 noon, the system is picking the material staging time at around 8:00 AM the same day and it is calculating the loading time & pick/pack time which is mentioned in the shipping point, whereas the material is not available in stock.
Pls. let me know from where it is picking the material staging time
Thanks in advance
Aravind
Hi,
i think material staging time is coming from GR Processing Time field in QM view of the material master..
PP consultants will define this time before starting production..
please go through this link..it may help u..
http://help.sap.com/saphelp_47x200/helpdata/en/c6/f840fb4afa11d182b90000e829fbfe/frameset.htm
regards..
yogi..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
answered
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
106 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.