Status for releasing project

Former Member
0 Kudos

Hi,

I have a project which is in created status.We are getting the Budget distribution from Investment Prgm as we are linking measure to project. T code IM52.

I want to have a control without Budget Distribution to the project, Nobody is allowed to release the project.

Let me know, how can i achive it.

Regards

N.Raju

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Create a user status and default it to all WBS Elements at the time of creation and block the release process using it. once the budget is distributed chnage the user status so that which shall allow the release of WBS Elements. Using authorizations u can control who can change the user status.

Regards

Murali

Former Member
0 Kudos

Hi Murali,

The way you said, same i have done it after posting this and tested. Its ok.

I am thinking, can we have any User exit wherein i can control the project before releasing budget without using User status profile.

Regards

N.Raju

Former Member
0 Kudos

I'm afraid i dont think any user exit is available for this purpose.

reagards

Murali

Former Member
0 Kudos

Thanks murali,

Iam closing this thread.

Regards

N.Raju