Hi,
I have a project which is in created status.We are getting the Budget distribution from Investment Prgm as we are linking measure to project. T code IM52.
I want to have a control without Budget Distribution to the project, Nobody is allowed to release the project.
Let me know, how can i achive it.
Regards
N.Raju
Create a user status and default it to all WBS Elements at the time of creation and block the release process using it. once the budget is distributed chnage the user status so that which shall allow the release of WBS Elements. Using authorizations u can control who can change the user status.
Regards
Murali