Dear Experts,
Can we see Budget in CJ20N Project builder ?
Regards&Thanks
chandra
Hi ,
Go in Project planning Board by
GOTO > Project Planning Board > in Project planning board Settings >> Field selection
Here u can select the budget column and can be displayed values which are posted thru CJ30
Rgds
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The report displays current budget. If budget release is applicable in your case, you need to release budget to make it current.
1. Goto CJ30, check if current budget is populated. If yes, report should show it. I have cross checked this. One possibility in this may be you are budgeting for 2008 and running report for different year.
2. Goto CJ20N, click on Proj Defn goto 'Control data' tab, check budget profile. Open this budget profile in OPS9 and see if 'release' is ticked.
Regards
No, you cant. If you wish to see structure and financials together you can use reports like CNS41. Change the layout to add reqd fields.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.