Hi Please guide me to proceed for displaying the report output as

On Execution Data to be Displayed

Object Description Object Number Budget - Overall

plan - Overall Actual - Overall Commitment - Overall

ROP - Overall Assigned - Overall Available - Overall

Budget - 2009 Plan - 2009 Actual - 2009

Commitment - 2009 ROP - 2009 Assigned - 2009

Available - 2009 Budget - 2010 Plan - 2010

Actual - 2010 Commitment - 2010 ROP - 2010

Assigned - 2010 Available - 2010

ALL THESE TITLES AS COLUMNS

Accepted Solutions (0)

Answers (1)

Answers (1)

ansar_shaikh2
Contributor
0 Kudos

1. CN42N - Overview of Project Definition

2. CN43N - Overview of WBS Elements

3. CN41 - Structure Overview

4. CN53N - Overview of Milestones

5. CN52N - Components Overview

6. ME5J - Purchase requisitions for Project

7. ME2J - Purchase Orders for Project

8. CNMM - Project Oriented Procurement

9. CN60 - Display change documents

10. S_ALR_87100185 Actual Costs for Each Month (Current Fiscal Year)

11. S_ALR_87100186 Planned Costs for Each Month (Current Fiscal Year)

12. S_ALR_87100187 Commitments for Each Month (Current Fiscal Year)

13. S_ALR_87013532 Plan/Actual/Variance

14. S_ALR_87013533 Plan/Actual/Commitment/Rem.Plan/Assigned

15. S_ALR_87013534 Plan1/Plan2/Act/Commitment

16. S_ALR_87013537 Commitment Detail

17. S_ALR_87013542 Actual/Commitment/Total/Plan in Control Area Currency

18. S_ALR_87013557 Budget/Actual/Variance

19. S_ALR_87013558 Budget/Actual/Commitment/Rem Plan/Assigned

20. S_ALR_87013560 Budget Updates

TRY CJI3 WITH DIFFRENT LAOUT, 1SAP, 2SAP, 3 SAP

TRY CJI8 FOR BUDGET REPORT

HOPE THIS WILL HELP YOU

REGARDS

ANSAR