capacity planning

Hi Friends,

please give me the required configuration settings for capacity planning in work centre in detail. my requirement is to view the load in each work centre. should i give finite scheduling or not. i am getting an error while creating production orders "No reqmts/caps exists or not relevant to finite scheduling"

please give solution

regards

Arun Kumar R V

Former Member
replied

Hi,

Use all standard SAP configuration,Capacity Leveling Profile.

Define time profile in OPD2.

Define the strategy profile in OPDB

Define the Overall profiles in OPD0.

Then only you need to to active your all work center for the finite scheduling at the bottom of capacity view in work center.(CR02)

Then run MRP with scheduling- 2 Lead time scheduling and capacity planning.(MD02)

You will get your capacity requirement in CM01, or CM25/CM21.

In rem you can use MF50.

Please try and revert back if you have any query on the same

[Capacity Planning|http://help.sap.com/saphelp_46c/helpdata/en/8a/a5a3154adc11d189740000e8322d00/frameset.htm]

Regards,

R.Brahmankar

Rewards if useful