on 08-11-2008 7:20 AM
Hi.
I am trying to set up Plan Driven procurement on SRM 5.0 and ECC6.00.
I used MRP to create purchase requisition. After the exection of MRP,
I found no entry created in the ERPTRANS table for the PR documents
generated by MRP.
However, after changing the MRP origin PR document with ME52N,
a entry for that PR document was inserted in the ERPTRANS table.
Also, I manually created a purchase requisition using ME51N,
an entry was inserted in ERPTRANS table too.
Are there any special settings necessary for MRP?
Thanks in advance for any advice.
HN
Hi
Did you verify your results inMD04 after your MRP run for the particular palnt?
regards
Muthu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi.
My question has been solved.
According to the note 656597, I should have activated the the 'Business Transaction Event' for the 'New Dimanesion Integration' (NDI).
https://websmp130.sap-ag.de/sap(bD1qYSZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=656597
Thnak you.
HN
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.